Narendra Modi says power plants with a total installed capacity of 20,000MW are lying idle in India due to a fuel shortage

Gujarat chief minister and Bharatiya Janata Party’s prime ministerial candidate Narendra Modi. Photo: Mint
Claim: Power plants with a total installed capacity of 20,000MW are lying idle in India due to a fuel shortage.
Who: Narendra Modi, Gujarat chief minister and Bharatiya Janata Party’s prime ministerial candidate.
When: At an event organized by lobby group Federation of Indian Chambers of Commerce and Industry in Gandhinagar.
Check: He is right.
While a natural gas-based capacity of 18,000MW is
operating at low plant load factor due to limited fuel availability,
projects totalling 8,000MW are stranded due to unavailability of gas.
Source: Ministry of power
Source: http://blog.livemint.com/Specials/va4NeWQ0XyTywkY343ne8J/Claim-Check-Narendra-Modi-on-power-projects-lying-idle-due.html